We’ve officially closed on project number 3! With this project, we bought a single family home on a double lot. We plan on severing the lot, building two tiny homes on it and selling the single family home separately! Let the fun begin!
Renderings of our next build!
Services are going in at our next build location: Project M!
Sneak peak behind the scenes of our manufacturing facility! Pictured are our next two houses in progress!
Lots of shop progress this week! Windows and doors have been installed and rough plumbing/ electrical have been run in the tiny home halves!
Prepping the site for the foundation at Project M!
Foundation prep continued! This is for the third unit at Project M which will be located above a 2 car garage
Gravels in at Project M! Foundation site is prepped for the underground plumbing to be dug!
Underground plumbing is in at Project M! Foundation is fully prepped and ready to be poured this week!
Birds eye view of the foundation being poured at Project M!
Helical pile foundation for the main house at Project M went in today!
Insulation is in on these two tiny home halves! Almost ready for transport!
Garage portion of the ADU at Project M is framed! This ADU will be a 2 car garage on the bottom with a 1 bedroom unit on top!
Roof is all built at Project M! Next week the walls will be trailered over to the site and craned into place on top of the garage!
Crane day at Project M!
Crane days are the most exciting days!! Project M’s 1 bedroom unit on top of a 2 car garage got assembled yesterday in 3.5 hours!!
Project M Updates: The floors for House A have been built (pictured in front of House B) And the stairway for House B is almost complete!
House A’s roof has been built! House B’s siding is almost complete on the exterior and HVAC/ electrical has begun on the interior!
The tiny home halves for Project M house A are coming along at the shop!! Loving the darker siding for this project. We can’t wait to transport the halves to the site in the next couple weeks!
Rough plumbing and electrical are complete at Project M! Ready for drywall to start on Monday
Drywall is all hung at Project M!
Yesterday was Project M House A’s crane day! This was our biggest crane day to date! We had 4 tiny home halves to assemble into place making up two- 1 bedroom units stacked on top of one another! This whole two storey was completed in a total of 6 hours!
House A stairs and House B eavestroughs are in the works at Project M!
Project M House B updates: – Garage doors are in – Drywall is all mudded & taped – First coat of paint is on – All the flooring is in!
Project M House A updates: Porches have been added – Siding is almost complete – Electrical’s going in! Loving those views from the second storey!
Interior doors, trim and kitchen cabinets are in at Project M House B!
Siding’s complete on Project M House A!
Project M updates: All railings are complete – Backsplash has been started in house B – All trim and crown moulding is up and painted in house B
Project M Updates: concrete forms for driveway and walkways are in, backsplash is complete & bathroom vanity is installed. Next up: light fixtures, appliances & handles!
Home stretch on House B at Project M!
Project M House B updates: Privacy screen installed – Interior & exterior lights installed – Bathroom fixtures installed. All this unit needs for completion is kitchen handles installed & a good cleaning!
Project M House A updates: upper unit- drywall is complete & first coat of paint is on – all the flooring is in – kitchen install is well under way!
Exterior of Project M!
Project M House A updates: Upper unit: interior doors & trim have been installed – cabinets, countertops, backsplash & handles are in. Lower unit: electrical & plumbing are in – drywall has been hung & the first coat of mud/ tape is complete
Project M House B unit is complete!
Light fixtures, taps & appliances are in at Project M’s house A upper unit!
Project M house A lower unit progress: – Mudding & taping is complete – First coat of paint is on – Exterior lights are installed
Driveway & walkways are in at Project M!
Project M lower unit progress: flooring is in – trim, kitchen cabinets & handles have been installed
Lights, countertops and bathroom vanity got installed in the lower unit at Project M! Homestretch!
Project M upper unit is almost complete! Just a couple finishing touches & it will be ready to be cleaned
Project M House A! Both the upper and lower units are staged to perfection! Coming soon to MLS!
Project M House B! A 1 bedroom unit upstairs and the lower garage portion staged as a man cave!
Those exterior shots of Project M!