Our next site, Project H2, is almost all prepped to begin! This 30 foot wide lot is going to become a triplex!
Underground services have begun at Project H2!
Underground plumbing is finished and the spikes for the foundation are in! These spikes act as a guide for where the helical piles will go!
Helical piles are in at Project H2!
The floor for the front house at project H2 is all built! Next up: building the roof and then the walls can be delivered!
The ADU’s floor is almost complete at Project H2! The main houses floor is sitting complete just in front
Flooring and cabinets are installed in the ADU at Project W! So much natural light from the upper windows in this model!
Walls are starting to go up for the primary house at Project H2!
First floor of the primary house at Project H2 is all framed up!
Second floor is framed and the roof trusses are on!
Front house progress at Project H2!
Roof is all framed and the decks are going on!
Stairs and decks are on the primary house at Project H2!
Sidings started at Project H2 main house!
Front house units at Project H2 are ready for drywall to begin!
Framing progress for the ADU at Project H2! We changed up the design for this build and built in stairs!
The ADU at Project H2 is all framed in!
Drywalls all hung and the first coat of mud/ tape is finished at the main house at Project H2!
Sidings going on the ADU at Project H2!
Project H2 is coming along! The ADU’s siding is almost complete & drywalling continues in the main houses two units!
Concrete forms are in place at Project H2! Ready for the walkways and driveway!