We’ve started our next project at the shop! Project SL consists of two 2- bedroom units stacked as the primary and a 1- bedroom ADU in behind. Our clients decided to switch things up and went with a different siding colour combination for this build!
Site prep has begun at our next build, Project SL! The trenches are all dug and ready for underground plumbing!
Screw pile foundation is in at Project SL!
The primary houses floor has been built at Project SL! Next up: the ADU’s floor!
Crane in day for the walls of the primary house for Project SL!
Second story of the primary unit at Project SL has been added!
Project SL primary building updates: Roof is on and shingled – Stairs have been built – Rough electrical is complete
Project SL ADU framing progress!
Project SL ADU Progress! All framed and roof is on! -majority of the windows are in – rough electrical -interior framing is almost complete! Almost ready for drywall!
Project SL primary house progress! -fire barrier is in – primary house units are ready for drywall!
ADU progress at Project SL! Our clients went with a custom cabinet colour, gold handles and butcher block counters for this unit! We love how this unit is coming together!
Home stretch at Project SL! Just a few finishing touches on the interior and it will be all done!
Project SL front units are all complete! we are loving the different variations of butcher block our clients went with
Project SL ADU finishes!