Our next build is Project A2, consisting of two- 2 bedroom units stacked with a 1- bedroom ADU in behind. The lower unit is currently all framed up in the shop!

   

March 22nd, 2023

Windows and siding have been installed for Project A2 in the shop!

 

 

April 3rd, 2023

Services are going in at Project A2!

  

May 1st, 2023

Project A2 updates! Both foundations are in – Framing has begun for the rear ADU – The primary houses’ roof has been built! Next up: continue framing the ADU & delivery of the primary houses’ pieces!

     

May 4th, 2023

Day 1 of crane in day at Project A2 complete! The lower two bedroom unit was craned into place today! Next up: move the second story floor in place and crane in the upper unit!

 

 

 

   

 

 

May 5th, 2023

Project A2 ADU framing coming along! We are loving the custom high ceilings and loft space this customer requested!

 

May 12th, 2023

Project A2 crane day #2! The two story primary house composed of two, 2- bedroom units stacked is now complete! Now onto the interior!

   

   

May 17th, 2023

Exterior updates at Project A2! The primary house has the roof on and the decks/ stairs are being added! The ADU is framed and exterior insulation is going up!

 

May 18th, 2023

Stairs and decks complete on the primary house at Project A2!

   

May 31st, 2023

Project A2 ADU Progress! This 1 bedroom, 1 bathroom with a loft design is coming together! We love all the windows and natural light this model has!

 

   

June 2nd, 2023

Drywall has begun at Project A2 primary house!

       

June 3rd, 2023

Those project A2 ADU angles!

June 6th,2023

Drywall is hung in the primary house at Project A2!

June 9th, 2023

Siding progress at Project A2!

   

 

June 19th, 2023

The ADU at project A2 is all ready for drywall! && the top unit has the floor laid, drywall complete and the first coat of paint is on!

   

 

July 13th, 2023

Project A2 exterior updates! This project is almost complete! stay tuned for interior shots!

 

July 17th, 2023

All 3 units at Project A2 have the drywall up, walls painted and flooring and kitchens installed!

   

July 31st, 2023

   

   

August 6th, 2023

Project A2 ADU interior updates! We love the natural light and openness of this model!

   

   

September 19th, 2023

Sneak peak! Project A2 is all furnished and ready for professional pictures! Stay tuned!

September 20th, 2023

Project A2 ADU interior final pictures! This is our 1 bedroom with a loft model sitting at 431 Sq Ft.

 

September 21st, 2023

Interior shots of the primary house at Project A2! The primary house is made up of two 2- bedroom units stacked on top of one another. Each 2- bedroom unit is 670 sq ft!

September 22nd, 2023

Exterior shots of Project A2!